Holidays are considered "non-working days" for purposes of your project schedules. 

When CoConstruct calculates task dates based on predecessors and work days, it will skip over any holidays that have been entered on your account (Main Menu > Settings > Holidays), just as it skips over non-working days that you have specified for the project.

If you add a new holiday in the settings of your account, you will need to re-publish your schedule for the dates to reflect the new non-working day.

Holidays are date specific - so you will need to enter your observed holidays for each year.

Author Picture

New to CoConstruct?

Get A DemoLearn More

Get a free demo

Fill out the form to get access to a full demo video now + a designated CoConstruct expert to answer all your questions.

By submitting your information, you are consenting to let CoConstruct maintain the data you provide and to contact you via phone or email.
Questions? Please read our full privacy policy.

SEE WHY 40,000+ BUILDING PROS RELY ON COCONSTRUCT

SCHEDULE A DEMO

Get a free demo

Fill out the form to get access to a full demo video now + a designated CoConstruct expert to answer all your questions.

By submitting your information, you are consenting to let CoConstruct maintain the data you provide and to contact you via phone or email.
Questions? Please read our full privacy policy.

Helpful Links

Start your demo

Get a free demo

Fill out the form to get access to a full demo video now + a designated CoConstruct expert to answer all your questions.

By submitting your information, you are consenting to let CoConstruct maintain the data you provide and to contact you via phone or email.
Questions? Please read our full privacy policy.

How It WorksPricingTestimonialsOur GuaranteeBuilder ResourcesLearn Construction Software